THE first phase of flood control works along the Mananga River in Talisay City in Cebu City is now 90% complete, with the Department of Public Works and Highways (DPWH) continuing construction of gabion structures and drainage facilities as part of efforts to improve the river’s capacity for runoff water.
DPWH Secretary Giovanni “Banoy” Lopez and Department of Transportation (DOTr) Secretary Vivencio “Vince” Dizon inspected the ongoing works last Thursday, to assess the project’s progress and discuss the next steps in mitigating flooding in Cebu.
Lopez said the remaining work in the first phase includes completing the drainage canal, which is intended to direct water toward the river, and adding more gabion structures.
He said the project would continue beyond the current phase to restore the river’s natural width and prevent its narrowing.
During the inspection, Lopez emphasized that the riverbed should have a width comparable to the bridge above.
He said the riverbed, previously measuring around 10 to 14 meters in some portions, is being widened to approximately 80 meters.
The wider area is intended to remain open as a riverbed, allowing water to flow through without being blocked by structures built along the riverbanks.
Lopez credited the local government, led by Talisay City Mayor Gerald Anthony “Samsam” Gullas, for establishing a no-build zone along the river. Signages marking the restricted areas had also been installed during an earlier inspection.
He said cooperation between the national and local governments is necessary to implement flood-control projects, particularly in keeping riverside areas free.
When asked whether the widened area could eventually be developed into a park, Dizon said that would be up to the local government.
Although the first phase is already 90% complete, the project will continue along the river, which stretches approximately 2.5 kilometers.
DPWH-7 Regional Director Engineer Simon Arias said succeeding portions of the project would depend on future budget allocations, including funding for 2028 and beyond.
Dizon said the continuing work should prioritize restoring the river to its natural width, noting its constriction had reduced the space available for water to flow.
He also said the inspection was part of the turnover of the administration’s priority flood-control projects in Cebu from him to Lopez, following the change in leadership at the DPWH.
Dizon said implementing the province’s 2017 flood mitigation master plan should remain a priority, particularly its proposed construction of dams and other water impounding structures.