The Philippines is seeking World Bank approval for a second extension of the Metro Manila Flood Management Project, as several critical pumping stations remain unfinished nearly a decade after the project was approved.
The long-delayed project is co-financed by the Asian Infrastructure Investment Bank (AIIB).
In a restructuring paper, the US-based multilateral lender said the proposed six-month extension would move the project’s loan closing date from Nov. 30, 2026, to May 31, 2027, in a bid to complete and commission remaining flood-control infrastructure.
The proposed restructuring follows the approval by the Economy and Development (ED) Council, chaired by President Marcos Jr., of a six-month extension of the project’s implementation period during its meeting last Nov. 11.
The World Bank disclosed that the Philippine government, through the Department of Finance (DOF), formally requested the restructuring last Nov. 24, citing cumulative delays that prevented several pumping stations from being completed before the existing deadline.
This would be the project’s second restructuring since its approval back in 2017, following an earlier two-year extension from November 2024 to November 2026.
The World Bank warned that without completing the remaining pumping stations, the project would achieve only 68 percent of its targeted reduction in flood-prone areas and benefit just 72 percent of its intended beneficiaries.
Even with the extension, the lender cautioned that Libertad, Tripa de Gallina, and Hagonoy pumping stations may not become fully operational by May next year if technical setbacks recur or typhoons disrupt construction.
According to the restructuring paper, the seven pumping stations facing significant implementation challenges include Tripa de Gallina, where narrow waterways and rainy-season conditions complicated construction, as well as Magsaysay, where the relocation of informal settler families (ISFs) delayed works.
Libertad faced an extended suspension due to an interagency land dispute, while Hagonoy required a specialized pipe-jacking method to minimize traffic disruptions.
At Uli-Uli, the revocation of a contractor’s license forced rebidding, while flooding near Tullahan River and restricted road access slowed construction at Acacia.
Tatalon also faced flooding, river backflow, as well as utility obstructions involving Manila Electric Co. (Meralco) power poles and Manila Water Co. Inc. utility lines, with floodwall construction remaining its main obstacle.
The World Bank projected completion of Tripa de Gallina, Magsaysay, Libertad, and Uli-Uli by February 2027, and Hagonoy, Acacia, and Tatalon by March next year, leaving time for testing, commissioning, as well as turnover before the revised deadline.
Despite delays, the World Bank retained its “moderately satisfactory” ratings for progress toward achieving the project’s development objective (PDO) and overall implementation progress, with overall risk assessed as “moderate.”
The restructuring paper showed that of the 38 existing pumping stations targeted for rehabilitation, only 19 were fully rehabilitated and operational, while construction of four new pumping stations remained ongoing.
Completed works had provided 75 cubic meters per second of additional pumping capacity against the 148-cubic-meter target, achieving 63.9 percent of the targeted reduction in flood-prone areas and 72.5 percent of the target for direct beneficiaries, according to the lender.
The project, jointly implemented by the Department of Public Works and Highways (DPWH) and the Metropolitan Manila Development Authority (MMDA), aims to benefit an estimated 1.05 million people through the rehabilitation as well as improvement of existing pumping stations, as well as the construction of new ones.
The World Bank reported that $136.2 million, or almost three-fourths of its reduced $184.94-million loan commitment, had been disbursed, leaving $48.74 million unspent.
However, the World Bank document showed that as of August, commitments exceeded 94 percent of revised component allocations for both the DPWH as well as the MMDA, while disbursements represented only about 58 percent of awarded DPWH contract costs and 66 percent of MMDA commitments.
The $500-million project, approved in September 2017 and effective since March 2018, was originally financed by $207.6 million each from the World Bank as well as the Beijing-based AIIB, alongside $84.79 million in Philippine government counterpart funding.
Its first restructuring, approved last Oct. 1, 2024, cancelled a combined $45.3 million from the two multilateral lenders’ loans, extended the original November 2024 closing date by two years, as well as revised project activities and targets due to implementation difficulties as well as land acquisition constraints.
The latest restructuring proposes no further loan cancellations or changes to the PDO, but would update its implementation schedule and disbursement estimates.